Renovated meat processing factory in Serbia goes for RubberGard EPDM

Extensive renovation works were carried out at the Mitros meat processing factory in Sremska Mitrovica, Serbia, following its acquisition by Gierlinger Holding, an Austrian company that specializes in processed meat products such as bacon, ham, sausages and spreads.

Project ID
Location

Sremska Mitrovica, Serbia

Project type

Renovation

Building type

Industrial building

Surface

9,000 m²

Products

Elevate RubberGard EPDM 1.1 mm

System

Fully adhered

The original 9,000 m² roof build-up, consisting of concrete elements covered with a bitumen membrane, was deteriorated and overstressed and needed to be renovated.

One of the main challenges of this project was that it was not possible to drill the concrete substrate. Therefore, a durable, non-penetrating roofing system was needed. In addition, the vaulted shape of the roof required a flexible membrane that could be installed quickly and easily.

After considering several different proposals, the building owner decided to go for a Elevate RubberGard EPDM fully adhered system, as proposed by a local Firestone partner. This experienced roofing contractor completed the renovation of the roofing system in 60 days.